Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The company would have the option to withdraw from the investment after 2 years if it turns out to be unprofitable.
B) The investment would increase the odds of the company being able to subsequently make a successful entry into China.
C) The investment would preclude the company from being able to make a profitable investment in China.
D) Competitors are considering similar investments in India, and the firm can discourage them from trying by entering now.
E) The new plant could be easily retrofitted to manufacture many of the firm's other products.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $1,311
B) $1,457
C) $1,619
D) $1,799
E) $1,999
Correct Answer
verified
Multiple Choice
A) No impact on the PV of expected cash flows, but risk will increase.
B) The PV of expected cash flows increases and risk decreases.
C) The PV of expected cash flows increases and risk increases.
D) The PV of expected cash flows decreases and risk decreases.
E) The PV of expected cash flows decreases and risk increases.
Correct Answer
verified
Multiple Choice
A) A company has an option to invest in a project today or to wait for a year before making the commitment.
B) A company has an option to close down an operation if it turns out to be unprofitable.
C) A company agrees to pay more to build a plant in order to be able to change the plant's inputs and/or outputs at a later date if conditions change.
D) A company invests in a project today to gain knowledge that may enable it to expand into different markets at a later date.
E) A company invests in a jet aircraft so that its CEO, who must travel frequently, can arrive for distant meetings feeling less tired than if he had to fly a commercial airline.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Its estimated capital budget is probably too small, because projects' NPVs are often larger when real options are taken into account.
B) Its estimated capital budget is probably too large due to its failure to consider abandonment and growth options.
C) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too large, but failing to consider growth and timing options probably makes the optimal capital budget too small, so it is unclear what impact the failure to consider real options has on the overall capital budget.
D) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too small, but failing to consider growth and timing options probably makes the optimal capital budget too large, so it is unclear what impact not considering real options has on the overall capital budget.
E) Real options should not have any effect on the size of the optimal capital budget.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Real options change the size, but not the risk, of projects' expected NPVs.
B) Real options change the risk, but not the size, of projects' expected NPVs.
C) Real options can reduce the cost of capital that should be used to discount a project's expected cash flows.
D) Very few projects actually have real options. They are theoretically interesting but of little practical importance.
E) Real options are more valuable when there is very little uncertainty about the true values of future sales and costs.
Correct Answer
verified
Multiple Choice
A) $202
B) $224
C) $249
D) $277
E) $308
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $1,857
B) $2,042
C) $2,246
D) $2,471
E) $2,718
Correct Answer
verified
Showing 1 - 20 of 39
Related Exams