Filters
Question type

Study Flashcards

It is not possible for abandonment options to decrease a project's risk as measured by the project's coefficient of variation.

A) True
B) False

Correct Answer

verifed

verified

Real options exist whenever managers have the opportunity, after a project has been implemented, to make operating changes in response to changed conditions that modify the project's cash flows.

A) True
B) False

Correct Answer

verifed

verified

Real options are valuable, and that value is correctly captured by a traditional NPV analysis. Therefore, there is no reason to consider real options separately from the NPV analysis.

A) True
B) False

Correct Answer

verifed

verified

Weisbach Electronics is considering investing in India. Which of the following factors would make the company less likely to proceed with the investment?


A) The company would have the option to withdraw from the investment after 2 years if it turns out to be unprofitable.
B) The investment would increase the odds of the company being able to subsequently make a successful entry into China.
C) The investment would preclude the company from being able to make a profitable investment in China.
D) Competitors are considering similar investments in India, and the firm can discourage them from trying by entering now.
E) The new plant could be easily retrofitted to manufacture many of the firm's other products.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

If a firm practices capital rationing, this means that it is accepting fewer projects than would be theoretically optimal; hence, it is not maximizing its theoretical value.

A) True
B) False

Correct Answer

verifed

verified

Real options are options to buy real assets, especially stocks, rather than interest-bearing assets, like bonds.

A) True
B) False

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1) protection options, (2) flexibility options, (3) timing options, and (4) abandonment options.

A) True
B) False

Correct Answer

verifed

verified

False

Winters Corp. is considering a new product that would require an investment of $20 million now, at t = 0. If the new product is well received, then the project would produce after-tax cash flows of $10 million at the end of each of the next 3 years (t = 1, 2, 3) , but if the market did not like the product, then the cash flows would be only $4 million per year. There is a 50% probability that the market will be good. The firm could delay the project for a year while it conducts a test to determine if demand is likely to be strong or weak, but it would have to incur costs to obtain this timing option. The project's cost and expected annual cash flows would be the same whether the project is delayed or not. The project's WACC is 11.0%. What is the value (in thousands) of the option to delay the project?


A) $1,311
B) $1,457
C) $1,619
D) $1,799
E) $1,999

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

Which one of the following statements best describes the most likely impact that a profitable abandonment option would have on a project's expected cash flow and risk?


A) No impact on the PV of expected cash flows, but risk will increase.
B) The PV of expected cash flows increases and risk decreases.
C) The PV of expected cash flows increases and risk increases.
D) The PV of expected cash flows decreases and risk decreases.
E) The PV of expected cash flows decreases and risk increases.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Which one of the following is an example of a "flexibility" option?


A) A company has an option to invest in a project today or to wait for a year before making the commitment.
B) A company has an option to close down an operation if it turns out to be unprofitable.
C) A company agrees to pay more to build a plant in order to be able to change the plant's inputs and/or outputs at a later date if conditions change.
D) A company invests in a project today to gain knowledge that may enable it to expand into different markets at a later date.
E) A company invests in a jet aircraft so that its CEO, who must travel frequently, can arrive for distant meetings feeling less tired than if he had to fly a commercial airline.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

The optimal capital budget is the size of the capital budget where the rate of return on the marginal project is equal to the marginal cost of capital.

A) True
B) False

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1) growth options, (2) flexibility options, (3) timing options, and (4) abandonment options.

A) True
B) False

Correct Answer

verifed

verified

True

Wahal Corporation uses the NPV method when selecting projects, and it does a reasonably good job of estimating projects' sales and costs. However, it never considers any real options that might be associated with projects. Which of the following statements is most likely to describe its situation?


A) Its estimated capital budget is probably too small, because projects' NPVs are often larger when real options are taken into account.
B) Its estimated capital budget is probably too large due to its failure to consider abandonment and growth options.
C) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too large, but failing to consider growth and timing options probably makes the optimal capital budget too small, so it is unclear what impact the failure to consider real options has on the overall capital budget.
D) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too small, but failing to consider growth and timing options probably makes the optimal capital budget too large, so it is unclear what impact not considering real options has on the overall capital budget.
E) Real options should not have any effect on the size of the optimal capital budget.

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

Traditionally, an NPV analysis assumes that projects will be accepted or rejected, which implies that they will be undertaken now or never. However, in practice, companies sometimes have a third choice--delay the decision until later, when more information will be available.

A) True
B) False

Correct Answer

verifed

verified

True

Which one of the following statements is most CORRECT?


A) Real options change the size, but not the risk, of projects' expected NPVs.
B) Real options change the risk, but not the size, of projects' expected NPVs.
C) Real options can reduce the cost of capital that should be used to discount a project's expected cash flows.
D) Very few projects actually have real options. They are theoretically interesting but of little practical importance.
E) Real options are more valuable when there is very little uncertainty about the true values of future sales and costs.

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

High Roller Properties is considering building a new casino at a cost of $10 million at t = 0. The after-tax cash flows the casino generates will depend on whether the state imposes a new income tax, and there is a 50-50 chance the tax will pass. If it passes, after-tax cash flows will be $1.875 million per year for the next 5 years. If it doesn't pass, the after-tax cash flows will be $3.75 million per year for the next 5 years. The project's WACC is 11.0%. If the tax is passed, the firm will have the option to abandon the project 1 year from now, in which case the property could be sold to net $6.5 million after tax at t = 1. What is the value (in thousands) of this abandonment option?


A) $202
B) $224
C) $249
D) $277
E) $308

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Traditional discounted cash flow (DCF) analysis--where a project's cash flows are estimated and then discounted to obtain an expected NPV--has been the cornerstone of capital budgeting since the 1950s. However, in recent years, it has been demonstrated that DCF techniques do not always lead to proper capital budgeting decisions due to the existence of real options.

A) True
B) False

Correct Answer

verifed

verified

An important part of the capital budgeting process is the post-audit, which involves comparing the actual results with those predicted by the project's sponsors and explaining why any differences occurred.

A) True
B) False

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1) natural resource options, (2) flexibility options, (3) timing options, and (4) abandonment options.

A) True
B) False

Correct Answer

verifed

verified

Games Unlimited Inc. is considering a new game that would require an investment of $20.0 million. If the new game is well received, then the project would produce cash flows of $9.5 million a year for 3 years. However, if the market does not like the new game, then the cash flows would be only $6.0 million per year. There is a 50% probability of both good and bad market conditions. The firm could delay the project for a year while it conducts a test to determine if demand would be strong or weak. The project's cost and expected annual cash flows would be the same whether the project is delayed or not. If the WACC is 9.0%, what is the value (in thousands) of the investment timing option?


A) $1,857
B) $2,042
C) $2,246
D) $2,471
E) $2,718

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

Showing 1 - 20 of 39

Related Exams

Show Answer