Filters
Question type

Study Flashcards

Capital rationing is the situation in which a firm can raise only a specified,limited amount of capital regardless of how many good projects it has.

A) True
B) False

Correct Answer

verifed

verified

True

Which one of the following statements is most CORRECT?


A) Real options change the size,but not the risk,of projects' expected NPVs.
B) Real options change the risk,but not the size,of projects' expected NPVs.
C) Real options can reduce the cost of capital that should be used to discount a project's expected cash flows.
D) Very few projects actually have real options.They are theoretically interesting but of little practical importance.
E) Real options are more valuable when there is very little uncertainty about the true values of future sales and costs.

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

Real options can affect the size of a project's expected NPV but not project's risk as measured by the standard deviation or coefficient of variation of the NPV.

A) True
B) False

Correct Answer

verifed

verified

Norris Production Company (NPC) is considering a project that has an up-front cost at t = 0 of $2,400.(All dollars in this problem are in thousands. ) The project's subsequent cash flows are critically dependent on whether a competitor's product is approved by the Food and Drug Administration.If the FDA rejects the competitive product,NPC's product will have high sales and cash flows,but if the competitive product is approved,that will negatively impact NPC.There is a 50% chance that the competitive product will be rejected,in which case NPC's expected cash flows will be $700 at the end of each of the next seven years (t = 1 to 7) .There is a 50% chance that the competitor's product will be approved,in which case the expected cash flows will be only $50 at the end of each of the next seven years (t = 1 to 7) .NPC will know for sure one year from today whether the competitor's product has been approved. ? NPC is considering whether to make the investment today or to wait a year to find out about the FDA's decision.If it waits a year,the project's up-front cost at t = 1 will remain at $2,400,the subsequent cash flows will remain at $700 per year if the competitor's product is rejected and $50 per year if the alternative product is approved.However,if NPC decides to wait,the subsequent cash flows will be received only for six years (t = 2 ...7) .In addition,once NPC knows the outcome of the FDA's decision,it will not take on the project if its NPV is negative. ? This is a risky project,so a WACC of 16.0% is to be used.If NPC chooses to wait a year before proceeding,what is the value (in thousand) of the timing option today? Do not round intermediate calculations. ?


A) $88.88
B) $92.75
C) $73.43
D) $77.29
E) $57.97

F) All of the above
G) A) and C)

Correct Answer

verifed

verified

D

Langston Labs has an overall (composite) WACC of 10%,which reflects the cost of capital for its average asset.Its assets vary widely in risk,and Langston evaluates low-risk projects with a WACC of 8%,average-risk projects at 10%,and high-risk projects at 12%.The company is considering the following projects:  Project  Risk  Expected Return  A  High 15% B  Average 12% C  High 11% D  Low 9% E  Low 6%\begin{array}{ccc}\text { Project } & \text { Risk } & \text { Expected Return } \\\text { A } & \text { High } & 15 \% \\\text { B } & \text { Average } & 12 \% \\\text { C } & \text { High } & 11 \% \\\text { D } & \text { Low } & 9 \% \\\text { E } & \text { Low } & 6 \%\end{array} ? Which set of projects would maximize shareholder wealth?


A) A and B.
B) A,B,and C.
C) A,B,and D.
D) A,B,C,and D.
E) A,B,C,D,and E.

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

Wahal Corporation uses the NPV method when selecting projects,and it does a reasonably good job of estimating projects' sales and costs.However,it never considers any real options that might be associated with projects.Which of the following statements is most likely to describe its situation?


A) Its estimated capital budget is probably too small,because projects' NPVs are often larger when real options are taken into account.
B) Its estimated capital budget is probably too large due to its failure to consider abandonment and growth options.
C) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too large,but failing to consider growth and timing options probably makes the optimal capital budget too small,so it is unclear what impact the failure to consider real options has on the overall capital budget.
D) Failing to consider abandonment and flexibility options probably makes the optimal capital budget too small,but failing to consider growth and timing options probably makes the optimal capital budget too large,so it is unclear what impact not considering real options has on the overall capital budget.
E) Real options should not have any effect on the size of the optimal capital budget.

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

Games Unlimited Inc.is considering a new game that would require an investment of $21.0 million.If the new game is well received,then the project would produce cash flows of $9.5 million a year for 3 years.However,if the market does not like the new game,then the cash flows would be only $6.8 million per year.There is a 50% probability of both good and bad market conditions.The firm could delay the project for a year while it conducts a test to determine if demand would be strong or weak.The project's cost and expected annual cash flows would be the same whether the project is delayed or not.If the WACC is 9.6%,what is the value (in thousands) of the investment timing option? Do not round intermediate calculations. ?


A) $1,274
B) $1,083
C) $1,592
D) $1,019
E) $1,147

F) All of the above
G) C) and E)

Correct Answer

verifed

verified

Which one of the following is NOT a real option?


A) The option to expand production if the product is successful.
B) The option to buy shares of stock if its price is expected to increase.
C) The option to expand into a new geographic region.
D) The option to abandon a project if cash flows turn out to be lower than expected.
E) The option to switch the type of fuel used in an industrial furnace to lower the cost of production.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

A firm's optimal capital budget consists of all independent projects with positive NPVs plus those mutually exclusive projects that have the highest positive NPVs.

A) True
B) False

Correct Answer

verifed

verified

High Roller Properties is considering building a new casino at a cost of $10.0 million at t = 0.The after-tax cash flows the casino generates will depend on whether the state imposes a new income tax,and there is a 50-50 chance the tax will pass.If it passes,after-tax cash flows will be $1.875 million per year for the next 5 years.If it doesn't pass,the after-tax cash flows will be $3.75 million per year for the next 5 years.The project's WACC is 11.0%.If the tax is passed,the firm will have the option to abandon the project 1 year from now,in which case the property could be sold to net $6.7 million after tax at t = 1.What is the value (in thousands) of this abandonment option? Do not round intermediate calculations. ?


A) $437
B) $457
C) $318
D) $418
E) $398

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Winters Corp.is considering a new product that would require an investment of $22 million now,at t = 0.If the new product is well received,then the project would produce after-tax cash flows of $11.0 million at the end of each of the next 3 years (t = 1,2,3) ,but if the market did not like the product,then the cash flows would be only $4 million per year.There is a 50% probability that the market will be good.The firm could delay the project for a year while it conducts a test to determine if demand is likely to be strong or weak,but it would have to incur costs to obtain this timing option.The project's cost and expected annual cash flows would be the same whether the project is delayed or not.The project's WACC is 10.0%.What is the value (in thousands) of the option to delay the project? Do not round intermediate calculations. ?


A) $2,678
B) $1,826
C) $2,556
D) $2,191
E) $2,434

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

If a firm practices capital rationing,this means that it is accepting fewer projects than would be theoretically optimal;hence,it is not maximizing its theoretical value.

A) True
B) False

Correct Answer

verifed

verified

Which of the following statements is CORRECT?


A) In general,the more uncertainty there is about market conditions,the more attractive it may be to wait before making an investment.
B) In general,the greater the strategic advantages of being the first competitor to enter a given market,the more attractive it probably is to wait before making an investment.
C) In general,the higher the discount rate,the more attractive it probably is to wait before making an investment.
D) In general,investment timing options are more valuable than abandonment options.
E) In general,abandonment options are rarely seen in the real world.

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

The following 2 problems must be kept together. The first problem can be used alone, but use the second problem ONLY if the first problem is also used. Exhibit 13.1 Texas Wildcatters Inc. (TWI) is in the business of finding and developing oil properties, then selling the successful ones to major oil companies. It is now considering a new potential field, and its geologists have developed the following data, shown in thousands of dollars. * t = 0 A $350 feasibility study would be conducted at t = 0. The results of this study would determine if the company should commence drilling operations or make no further investment and abandon the project. There is an 80% probability that the feasibility study would indicate that an exploratory well should be drilled. There is a 20% probability that no further work would be done. * t = 1 If the feasibility study indicates good potential, the firm would spend $1,200 at t = 1 to drill an exploratory well. The best estimate is that there is a 60% probability that the exploratory well would indicate good potential and thus that further work would be done, and a 40% probability that the outlook would be poor and the project would be abandoned. * t = 2 If the exploratory well tests positive, the firm would go ahead and spend $8,000 to obtain an accurate estimate of the amount of oil in the field at t = 2. * t = 3 If the full drilling program is carried out, there is a 50% probability of finding a lot of oil and receiving $25,000 cash inflow at t = 3, and a 50% probability of finding less oil and then receiving only a $8,000 inflow. * Since the project is considered to be quite risky, a 18.00% cost of capital is used. -Refer to Exhibit 13.1 and to the previous problem.Calculate the project's coefficient of variation.(Hint: Use the expected NPV as found in previous problem. )


A) 5.47
B) 3.42
C) 4.56
D) 3.87
E) 4.33

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

Weisbach Electronics is considering investing in India.Which of the following factors would make the company less likely to proceed with the investment?


A) The company would have the option to withdraw from the investment after 2 years if it turns out to be unprofitable.
B) The investment would increase the odds of the company being able to subsequently make a successful entry into China.
C) The investment would preclude the company from being able to make a profitable investment in China.
D) Competitors are considering similar investments in India,and the firm can discourage them from trying by entering now.
E) The new plant could be easily retrofitted to manufacture many of the firm's other products.

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Chrustuba Inc.is evaluating a new project that would cost $8.6 million at t = 0.There is a 50% chance that the project would be highly successful and generate annual after-tax cash flows of $5.6 million during Years 1,2,and 3.However,there is a 50% chance that it would be less successful and would generate only $1 million for each of the 3 years.If the project is highly successful,it would open the door for another investment of $11 million at the end of Year 2,and this new investment could be sold for $22 million at the end of Year 3.Assuming a WACC of 9.5%,what is the project's expected NPV (in thousands) after taking into account this growth option? Do not round intermediate calculations. ​


A) 0$3,123
B) 0$3,471
C) 0$4,165
D) 0$2,603
E) 0$2,950

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Gleason Research regularly takes real options into account when evaluating its proposed projects.Specifically,it considers the option to abandon a project whenever it turns out to be unsuccessful (the abandonment option) ,and it evaluates whether it is better to invest in a project today or to wait and collect more information (the investment timing option) .Assume the proposed projects can be abandoned at any time without penalty.Which of the following statements is CORRECT?


A) The abandonment option tends to reduce a project's NPV.
B) The abandonment option tends to reduce a project's risk.
C) If there are important first-mover advantages,this tends to increase the value of waiting a year to collect more information before proceeding with a proposed project.
D) A project can either have an abandonment option or an investment timing option,but never both.
E) Investment timing options always increase the value of a project.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

B

Real options exist whenever managers have the opportunity,after a project has been implemented,to make operating changes in response to changed conditions that modify the project's cash flows.

A) True
B) False

Correct Answer

verifed

verified

Traditionally,an NPV analysis assumes that projects will be accepted or rejected,which implies that they will be undertaken now or never.However,in practice,companies sometimes have a third choice--delay the decision until later,when more information will be available.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following statements best describes the most likely impact that a profitable abandonment option would have on a project's expected cash flow and risk?


A) No impact on the PV of expected cash flows,but risk will increase.
B) The PV of expected cash flows increases and risk decreases.
C) The PV of expected cash flows increases and risk increases.
D) The PV of expected cash flows decreases and risk decreases.
E) The PV of expected cash flows decreases and risk increases.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Showing 1 - 20 of 41

Related Exams

Show Answer