A) $54.62
B) $57.49
C) $60.52
D) $63.54
E) $66.72
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
Multiple Choice
A) More of Project A's cash flows occur in the later years.
B) More of Project B's cash flows occur in the later years.
C) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
D) The NPV profile graph is inconsistent with the statement made in the problem.
E) The crossover rate, i.e., the rate at which Projects A and B have the same NPV, is greater than either project's IRR.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
Multiple Choice
A) $185.90
B) $197.01
C) $208.11
D) $219.22
E) $230.32
Correct Answer
verified
Multiple Choice
A) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
B) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
C) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPVs of relatively risky projects should be found using relatively low WACCs.
Correct Answer
verified
Multiple Choice
A) 9.43%
B) 9.91%
C) 10.40%
D) 10.92%
E) 11.47%
Correct Answer
verified
Multiple Choice
A) 1.88 years
B) 2.09 years
C) 2.29 years
D) 2.52 years
E) 2.78 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 13.13%
B) 14.44%
C) 15.89%
D) 17.48%
E) 19.22%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV) , then discounting the TV at the WACC.
B) A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV) , then discounting the TV to find the IRR.
C) If a project's IRR is smaller than the WACC, then its NPV will be positive.
D) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost.
E) If a project's IRR is positive, then its NPV must also be positive.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR.
D) If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR.
E) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
Correct Answer
verified
Multiple Choice
A) For a project with normal cash flows, any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV.
C) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
E) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35
Correct Answer
verified
Multiple Choice
A) $5.47
B) $6.02
C) $6.62
D) $7.29
E) $7.82
Correct Answer
verified
Showing 1 - 20 of 108
Related Exams