A) the npv profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
B) an npv profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
C) an npv profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
D) we cannot draw a project's npv profile unless we know the appropriate cost of capital for use in evaluating the project's npv.
E) an npv profile graph shows how a project's payback varies as the cost of capital changes.
Correct Answer
verified
Multiple Choice
A) assuming the timing pattern of the two projects' cash flows is the same, project b probably has a higher cost (and larger scale) .
B) assuming the two projects have the same scale, project b probably has a faster payback than project a.
C) the crossover rate for the two projects must be 12%.
D) since b has the higher irr, then it must also have the higher npv if the crossover rate is less than the cost of capital of 12%.
E) the crossover rate for the two projects must be less than 12%.
Correct Answer
verified
Multiple Choice
A) the crossover rate must be greater than 10%.
B) if the cost of capital is 8%, project x will have the higher npv.
C) if the cost of capital is 18%, project y will have the higher npv.
D) project x is larger in the sense that it has the higher initial cost.
E) the crossover rate must be less than 10%.
Correct Answer
verified
Multiple Choice
A) project d is probably larger in scale than project c.
B) project c probably has a faster payback.
C) project c probably has a higher irr.
D) the crossover rate between the two projects is below 12%.
E) project d probably has a higher irr.
Correct Answer
verified
Multiple Choice
A) 9.70%
B) 10.78%
C) 11.98%
D) 13.31%
E) 14.64%
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66
Correct Answer
verified
Multiple Choice
A) $92.37
B) $96.99
C) $101.84
D) $106.93
E) $112.28
Correct Answer
verified
Multiple Choice
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90
Correct Answer
verified
Multiple Choice
A) one drawback of the regular payback is that this method does not take account of cash flows beyond the payback period.
B) if a project's payback is positive, then the project should be accepted because it must have a positive npv.
C) the regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
D) one drawback of the discounted payback is that this method does not consider the time value of money, while the regular payback overcomes this drawback.
E) the shorter a project's payback period, the less desirable the project is normally considered to be by this criterion.
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the higher the cost of capital used to calculate the npv, the lower the calculated npv will be.
B) if a project's npv is greater than zero, then its irr must be less than the cost of capital.
C) if a project's npv is greater than zero, then its irr must be less than zero.
D) the npvs of relatively risky projects should be found using relatively low costs of capital.
E) a project's npv is generally found by compounding the cash inflows at the cost of capital to find the terminal value (tv) , then discounting the tv at the irr to find its pv.
Correct Answer
verified
Multiple Choice
A) if two projects are mutually exclusive, then they are likely to have multiple irrs.
B) if a project is independent, then it cannot have multiple irrs.
C) multiple irrs can occur only if the signs of the cash flows change more than once.
D) if a project has two irrs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
E) for a project to have more than one irr, then both irrs must be greater than the cost of capital.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) the discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) the net present value method (npv) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) the modified internal rate of return method (mirr) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) the internal rate of return method (irr) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 108
Related Exams