A) $2,549
B) $18,970
C) $4,571
D) $20,001
E) $1,348
Correct Answer
verified
Multiple Choice
A) $12,551
B) $12,877
C) $12,225
D) $16,125
E) $14,833
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $33,177
B) $22,409
C) $48,750
D) $26,483
E) $22,991
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project A,which has average risk and an IRR = 9%.
B) Project B,which has below-average risk and an IRR = 8.5%.
C) Project C,which has above-average risk and an IRR = 11%.
D) Without information about the projects' NPVs we cannot determine which one or ones should be accepted.
E) All of these projects should be accepted as they will produce a positive NPV.
Correct Answer
verified
Multiple Choice
A) An example of a sunk cost is the cost associated with restoring the site of a strip mine once the ore has been depleted.
B) Sunk costs must be considered if the IRR method is used but not if the firm relies on the NPV method.
C) A good example of a sunk cost is a situation where a bank opens a new office,and that new office leads to a decline in deposits of the bank's other offices.
D) A good example of a sunk cost is money that a banking corporation spent last year to investigate the site for a new office,then expensed that cost for tax purposes,and now is deciding whether to go forward with the project.
E) If sunk costs are considered and reflected in a project's cash flows,then the project's calculated NPV will be higher than it otherwise would have been had the sunk costs been ignored.
Correct Answer
verified
Multiple Choice
A) A sunk cost is any cost that must be expended in order to complete a project and bring it into operation.
B) A sunk cost is any cost that was expended in the past but can be recovered if the firm decides not to go forward with the project.
C) A sunk cost is a cost that was incurred and expensed in the past and cannot be recovered if the firm decides not to go forward with the project.
D) Sunk costs were formerly hard to deal with,but once the NPV method came into wide use,it became possible to simply include sunk costs in the cash flows and then calculate the project's NPV.
E) A good example of a sunk cost is a situation where Home Depot opens a new store,and that leads to a decline in sales of one of the firm's existing stores.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) -$43,339
B) -$33,804
C) -$28,170
D) -$46,199
E) -$36,433
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A)
B) Under current laws and regulations,corporations must use straight-line depreciation for all assets whose lives are 5 years or longer.
C) Corporations must use the same depreciation method (e.g. ,straight line or accelerated) for stockholder reporting and tax purposes.
D) Since depreciation is not a cash expense,it has no effect on cash flows and thus no effect on capital budgeting decisions.
E) Under bonus depreciation,higher depreciation charges occur at t = 0,and this increases the initial investment outlay and thus lowers a project's projected NPV.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Since the building has been paid for,it can be used by another project with no additional cost.Therefore,it should not be reflected in the cash flows of the capital budgeting analysis for any new project.
B) If the building could be sold,then the after-tax proceeds that would be generated by any such sale should be charged as a cost to any new project that would use it.
C) This is an example of an externality,because the very existence of the building affects the cash flows for any new project that Rowell might consider.
D) Since the building was built in the past,its cost is a sunk cost and thus need not be considered when new projects are being evaluated,even if it would be used by those new projects.
E) If there is a mortgage loan on the building,then the interest on that loan would have to be charged to any new project that used the building.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Adjusting the discount rate upward if the project is judged to have above-average risk.
B) Adjusting the discount rate upward if the project is judged to have below-average risk.
C) Reducing the NPV by 10% for risky projects.
D) Picking a risk factor equal to the average discount rate.
E) Ignoring risk because project risk cannot be measured accurately.
Correct Answer
verified
Multiple Choice
A) Changes in net operating working capital attributable to the project.
B) Previous expenditures associated with a market test to determine the feasibility of the project,provided those costs have been expensed for tax purposes.
C) The value of a building owned by the firm that will be used for this project.
D) A decline in the sales of an existing product,provided that decline is directly attributable to this project.
E) The salvage value of assets used for the project that will be recovered at the end of the project's life.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 73
Related Exams